Western Australia · SWIS · Distribution

Connect to Western Power - SWIS distribution & embedded generation.

For commercial and industrial load, and embedded generation from rooftop-scale through to multi-megawatt plant, on the SWIS distribution network.

At a glance

The SWIS distribution track

RulebookWestern Power's distribution connection processes - the NER does not apply
Who you deal withWestern Power; AEMO's WA functions for market registration questions on larger plant
Indicative timelineCommonly months rather than years for straightforward connections
ScopeLoad and embedded generation, rooftop-scale through multi-megawatt

Quick answers

SWIS distribution, quickly

Who do I apply to for a SWIS distribution connection?

Western Power, through its published connection channels, with site, load and generation details. The NER does not apply on the SWIS - these are Western Power's own distribution connection processes.

Will my plant face export limits?

Possibly. Inverter-based systems may face export limits reflecting local hosting capacity - what the local network can absorb shapes what your plant is allowed to export, and discovering that late reshapes the business case.

Does my embedded generator need power system studies?

Lighter than transmission, but not nominal: larger embedded generators commonly need power system modelling to support protection coordination and voltage management - and batteries add charge/discharge and control-mode behaviour to the assessment.

How long does a SWIS distribution connection take?

Commonly months rather than years for straightforward connections; network augmentation, protection complexity or constrained local capacity extend it. Early enquiry with realistic plant data is the cheapest acceleration available.

When does a SWIS project outgrow the distribution framework?

When scale, export or network impact pushes it onto the transmission track - Western Power's five-stage process, with its staged PowerFactory and PSCAD modelling. Projects that grow mid-development can cross that boundary, so map both tracks early.

Do market registration obligations apply to distribution-connected generators in WA?

They can for larger generating plant - WEM registration questions sit with AEMO's WA functions, so confirm market obligations early even on the distribution track.

The pathway

Six steps to energisation

  1. Connection enquiry or application

    Through Western Power's published connection channels, with site, load and generation details.

  2. Network assessment

    Western Power assesses capacity, voltage and protection impacts at the proposed connection point.

  3. Technical requirements issued

    Protection settings, export arrangements and any monitoring or control requirements - inverter-based systems may face export limits reflecting local hosting capacity.

  4. Offer and agreement

    Connection offer, contribution to any required network works, executed agreement.

  5. Network and customer works

    Delivered to Western Power's standards, with inspection and witnessing as required.

  6. Commissioning and energisation

    Compliance evidence, protection testing, then connection.

APD technician in hi-vis testing a protection relay on the repurposed 33 kV switchboard

Studies

Lighter than transmission - not nominal

Protection coordinationLarger embedded generators commonly need modelling to support protection coordination.
Voltage managementAssessment of voltage impacts at the connection point and along the feeder.
Power system modellingScaled to size - stepping up where export, fault level or power quality impacts warrant it.
BESS control behaviourBatteries add charge/discharge and control-mode behaviour to the assessment.

Where a project outgrows the distribution framework, the five-stage transmission track takes over - with a very different study load.

The honest part

Where it gets hard

Hosting capacity and export limits

What the local network can absorb shapes what your plant is allowed to export - and discovering that late reshapes the business case. APD assesses connection points before the application is lodged.

The distribution-to-transmission boundary

Projects that grow mid-development can cross into the five-stage transmission process. Worth mapping both tracks early with a team that runs both - power system studies.

Official documents

Western Power's own pages

Last reviewed: October 2026 · Always confirm current requirements with the network directly.

Proof, not promises

APD in Western Australia

Flat Rocks AI turbine inspection

WA renewables

Wind, delivered

APD's WA project record runs from wind farms to substations - see the full portfolio.

Projects →
Two engineers inspecting a large power transformer with HV bushings

Network works

Design to delivery

Connection works engineered and delivered - transformers, switchgear and the compliance evidence behind them.

EPC delivery →

Keep navigating

SWIS transmission

The five-stage track for transmission-connected plant.

Open →

Horizon Power

Regional WA's standalone microgrids - a different framework again.

Open →

BESS grid connection

Battery-specific studies and connection engineering.

Explore →

Pathway summarised from the network's published connection process as at October 2026. Processes, fees and thresholds change - the network's own documents are the authority.