Engaged by Enerven and ElectraNet, APD Global delivered the detailed engineering design supporting the connection of Summerfield BESS 1 & 2 to ElectraNet's transmission network.
Now in its commissioning phase, the 240 MW / 960 MWh project includes a new 275 kV substation, brownfield augmentation works and approximately 17 km of transmission infrastructure - bringing together APD Global's multidisciplinary expertise to deliver a safe, reliable and constructible design solution, supporting South Australia's target of 100% net renewable energy by 2027.
It is the same connected scope APD Global carries on storage projects across the NEM and WEM: the substation design, the transmission infrastructure and the BESS grid connection engineering that gets large-scale storage onto the network.