At a glance
Victoria at a glance
Quick answers
Victoria, quickly
Who manages Victorian transmission connections now?
VicGrid. Victorian transmission connections transferred from AEMO to VicGrid on 1 November 2025 - VicGrid manages the connection process for the declared shared network, including enquiries, applications, agreements and commissioning.
What does AusNet still do?
AusNet remains the declared transmission system operator (DTSO): it owns and operates most of the physical assets, delivers works on them, and is a party to the agreements that put your connection on its network.
Does NER Chapter 5 still apply in Victoria?
Yes. The spine - enquiry, application, 5.3.4A performance standards, registration, R1/R2 - is unchanged; the process owner is what differs from other NEM regions.
What is the declared shared network?
Victoria's transmission network - the NEM's structural exception. AusNet owns and operates most of the physical assets as the declared transmission system operator, while a separate body - now VicGrid - manages connection to it.
Who assesses my models in Victoria?
Submissions can involve VicGrid as process manager, AusNet as asset owner and AEMO on standards and registration - so model consistency across audiences matters even more than usual.
How long does a Victorian connection take?
Comparable to other NEM regions for the engineering stages - with an honest caveat: new arrangements are bedding in after the 1 November 2025 transfer, and process transitions can add coordination time. Build it into the programme rather than discovering it.
The pathway
The Victorian path to an agreement
- Pre-feasibility
Feasibility studies, connection options and early technical reviews are available ahead of the formal process.
- Connection enquiry
Lodged through the declared-network process VicGrid manages, under the NER framework.
- Connection application
Detailed plant data, proposed performance standards and the models behind them.
- Performance standards and system strength
Negotiated with AEMO under clause 5.3.4A and assessed as elsewhere in the NEM.
- Connection agreements
With the parties delivering the physical connection, including AusNet for works on its assets.
- Construction, registration and commissioning
Through to R1/R2 validation.
Studies
The standard suite - with more audiences
Victoria's institutional structure does not change the studies - it changes the coordination. Submissions can involve VicGrid, AusNet and AEMO, so model consistency across audiences matters even more than usual. Power system studies.
The honest part
Where it gets hard
Process manager (VicGrid), asset owner (AusNet) and AEMO on standards - mapping the interfaces on day one rewards proponents. APD has taken Victorian projects through AEMO connection and registration, the Carwarp Solar Farm among them. The studies story.
The VicGrid transfer took effect on 1 November 2025 - this page is re-checked quarterly, and your project team should check VicGrid's current guidance at each gate.
Official documents
VicGrid's and AusNet's own pages
Last reviewed: October 2026 · Always confirm current requirements with the network directly.
Proof, not promises
APD in Victoria
Carwarp Solar Farm
Taken through AEMO connection and registration in the NEM's southern regions - alongside Glenellen in NSW.
The studies story →
Yallourn
Switchgear engineering delivered inside one of Victoria's biggest power stations.
EPC delivery →Keep navigating