Home · Services · Grid Connection Navigator · NEM - AEMO process

National Electricity Market · All NEM regions

Connect in the NEM - the Chapter 5 spine.

NSW, Victoria, Queensland, South Australia, Tasmania and the ACT share one connection spine: NER Chapter 5, run through your local network with AEMO on standards and registration.

At a glance

One rulebook, five-plus networks

RulebookChapter 5 of the National Electricity Rules
Who you deal withThe local network service provider, with AEMO on performance standards and registration
Indicative timelineCommonly a year or more from enquiry to connection agreement for transmission-scale plant
ScopeTransmission-scale generation, storage and large loads across all NEM regions

Quick answers

Chapter 5, quickly

What is clause 5.3.4A?

The NER clause under which generator performance standards are negotiated between the proponent, the network service provider and AEMO. Every standard agreed is a promise the plant must keep through commissioning and beyond.

What are R1 and R2?

The staged model validation submissions through commissioning: proof that the plant as built and as tested performs the way the registered models said it would.

Do I need both RMS and EMT models?

For most transmission-connected generation and storage, yes. Assessors work in both domains: RMS (typically PSS®E) for wide-area dynamics and EMT (PSCAD) for the fast inverter control behaviour RMS cannot resolve, particularly near low-system-strength connection points - with documentation that lets the assessing engineers run each model independently.

What happens if my plant adversely affects system strength?

The proponent generally either funds remediation works or pays the network's system strength charges, depending on the framework in that region. It applies most often to inverter-based plant connecting in weaker parts of the network - and it is one of the most common sources of unexpected cost and schedule movement.

What makes NEM connection timelines blow out?

Performance standard negotiation and system strength remediation running multiple rounds. Resubmission is the silent schedule killer: networks will accept a second round of studies, but proponents carrying liquidated damages pay for it in money, not just months.

How do large loads fit the Chapter 5 process?

They negotiate load performance standards on a parallel track in place of a GPS - the enquiry, application and offer spine is shared. See data centres & large loads.

Which networks run the Chapter 5 process?

Each region's network service provider: Transgrid (NSW/ACT), Powerlink (QLD), ElectraNet (SA), TasNetworks (TAS) and VicGrid for Victoria's declared shared network - plus the distributors under Chapter 5A.

The pathway

Eight moves from enquiry to R2

  1. Pre-enquiry scoping

    Connection point options, indicative system strength, land and easement reality checks.

  2. Connection enquiry (5.3.2)

    Lodged with the network service provider; the response frames the technical envelope.

  3. Connection application

    Detailed plant data, proposed performance standards and the models behind them.

  4. Performance standard negotiation (5.3.4A)

    Agreed between proponent, network and AEMO; large loads negotiate load performance standards on the parallel track.

  5. System strength assessment

    And remediation or charges where the plant's impact requires it.

  6. Offer to connect and connection agreement

    The commercial gate into delivery.

  7. Registration with AEMO

    Market and technical registration ahead of energisation.

  8. R1 commissioning and R2 validation

    Staged proof that the plant performs as the registered models said it would.

Replacement 6.6 kV switchboard panels installed at Vales Point Power Station

Studies

The study suite, in the assessors' tools

System strengthAssessed behind the application - and the most common source of late cost movement.
Fault level & thermalFault level and thermal capability studies at and around the connection point.
Voltage stabilityWide-area behaviour under contingencies.
PSCAD EMTThe fast inverter control behaviour RMS cannot resolve - critical near weak connection points.
PSS®E RMSWide-area dynamics for GPS compliance modelling and negotiation.
PowerFactory steady-stateWhere networks require it - with model documentation reviewers can run independently.

Batteries add grid-forming or grid-following control validation and any SIPS obligations - BESS grid connection & studies.

The honest part

Where it gets hard

Model acceptance rounds

AEMO and the networks assess your RMS and EMT models in detail, and models that cannot be run independently or that disagree between domains go back. APD's submissions are built to pass the first time.

GPS negotiation

Clause 5.3.4A is a negotiation, not a form: every standard you agree to is a promise your plant must keep through R2 and beyond - negotiate from validated models.

System strength remediation

A weak connection point can add remediation works or charges that reshape project economics late. Early, honest assessment is the protection - grid connection services.

Official documents

The rules and AEMO's guidance

Last reviewed: October 2026 · Always confirm current requirements with the network directly.

Proof, not promises

APD in the NEM

Engineer in hi-vis at the Eraring BESS grid connection, facing the switchyard's steel transmission structures

NSW · 330 kV

Eraring BESS

Grid connection design for a utility-scale battery at one of the NEM's biggest sites.

The project →
Simulated versus measured model validation traces from generator performance standard testing

Registration

GPS, proven

Performance standards negotiated and validated - across the NEM and the WEM, 15 GW+ of connection studies.

The GPS case →
Wind turbine above farmland in the Central West Orana Renewable Energy Zone

REZ

Central-West Orana

Engineering inside Australia's first declared Renewable Energy Zone.

The project →

Keep navigating

Transgrid (NSW & ACT)

The Chapter 5 process as Transgrid runs it.

Open →

NEM distribution

Embedded generation under Chapter 5A - and the 5 MW step-up.

Open →

Power system studies

PSCAD, PSS®E and PowerFactory - proponent-side.

Explore →

Pathway summarised from the network's published connection process as at October 2026. Processes, fees and thresholds change - the network's own documents are the authority.