5. The connection layer, briefly
The fourth layer is the rulebook that justifies the substation existing at all. In the NEM, connections run under Chapter 5 of the National Electricity Rules through AEMO's processes, and the transmission owners publish their design standards under the NER's transparency clauses. In Western Australia the framework is the Electricity Networks Access Code, the WEM Rules and the Technical Rules - not the NER - and the distinction shapes everything from study scope to approval gates. That layer has its own reference: the grid connection process in Australia, every study explained.
Frequently asked questions
What standards govern substation design in Australia?
Four layers at once. AS 2067 - the Australian standard for substations and high-voltage installations exceeding 1 kV - sets the base, alongside AS/NZS 7000 for overhead lines, the IEC 60076 series for transformers and IEEE 80 for earthing. Each network owner then applies its own published design standards, which are frequently stricter. Secondary systems are designed to IEC 61850. And the connection itself runs under the National Electricity Rules in the NEM or the Technical Rules and WEM arrangements in Western Australia. A compliant design satisfies all four layers at once.
What is AS 2067?
AS 2067:2016 - Substations and high voltage installations exceeding 1 kV a.c. - is the spine of Australian substation design. It sets the minimum requirements for the design and erection of high-voltage installations: electrical clearances and safety distances, equipment selection, protection against fire and arc faults, risk-based earthing, and inspection and testing. Every Australian switchyard is measured against it, and most network owners' own standards build on it with stricter tables of their own.
Do all Australian network owners publish substation design standards?
No - and the asymmetry catches people. Transgrid, Western Power, Powerlink, TasNetworks, Ausgrid, Endeavour Energy and Energy Queensland all publish substantial substation design standards or libraries. The Victorian distributors publish embedded-generation access standards and the Victorian Service & Installation Rules instead of a public substation design suite, and ElectraNet and AusNet's transmission business issue design requirements per project through functional specifications rather than a published library.
Is IEEE 80 still the standard for substation earthing?
IEEE 80-2013 remains the industry-standard guide for AC substation earthing - the step and touch voltage limits, grid current and soil modelling methodology cited across Australian practice - although IEEE SA has listed it as Inactive-Reserved since March 2024. In Australia it is applied alongside AS 2067's risk-based earthing requirements and the ENA's EG-0 and EG-1 guides, and several network owners name all three in their own earthing standards.
What actually changes when designing to different network owners' standards?
The physics never changes - the compliance evidence does. Clearance and layout tables differ from AS 2067's baseline and from each other; earthing standards weight risk-based ENA EG-0 methods and deterministic IEEE 80 methods differently; preferred plant, busbar arrangements, drafting conventions and review gates are all owner-specific; and most owners require formal designer accreditation before work is accepted. A technically sound design to the wrong network standard is a rejected design.
Talk to the team that designs to them
APD Global delivers substation design and engineering up to 500 kV - accredited with the major Australian network owners and designing to their current standards, not a three-year-old memory of them. For how those standards play out on a real project, start with the guide to substation design in Australia.
Standards and network-owner documents linked above are the publishers' own authoritative sources, current at November 2026. Standards move - always confirm the current edition with the publisher or the network owner before relying on it.